North-South Expressway, section of National Highway (QL) 45 - Nghi Son, Thanh Hoa province, passing through Industrial Park No. 3 - Nghi Son EZ is speeding up construction, striving to open f

Đăng ngày Wednesday, 02/August/2023 bởi Quản trị viên

TPO - The Ministry of Transport said that the North-South expressway project on the National Highway (QL) 45 - Nghi Son section has just solved the last problem in terms of ground and is urgently constructing, striving to "reach the finish line" on the occasion of February 2. 9 to come.

Highway 45 - Nghi Son belongs to the North - South expressway component project running through Thanh Hoa province. It is expected that from September 2, it will be possible to run smoothly from Hanoi to Nghe An and vice versa.

Currently, the project's starting point at the section connecting with Mai Son - National Highway 45 has been opened to traffic on the occasion of April 30; The end point of the project is the intersection with Nghi Son - Dien Chau expressway in Nghi Son town (Thanh Hoa), Nghi Son - Dien Chau expressway also plans to open to traffic on September 2.

Talking to PV Tien Phong  about the construction status and the ability to complete the project on schedule, Mr. Nguyen Ngoc Quynh - Director of the National Highway 45 - Nghi Son Expressway Project Management Board, Project Management Unit 2, Ministry of Transport - said that, currently, the overall construction volume of the project has reached 80%, especially the XL01 and XL02 packages reach 90%. With the site for project construction, Mr. Quynh said that in early July, the project had solved the last problems about the ground on the main line.

At the soft soil treatment sections, currently the project is only about 1 km in the XL03 package, which must be monitored closely. "However, according to the plan on August 5, 1 km of settlement monitoring in package XL3 will be unloaded. After the ground is settled and the final settlement monitoring section is unloaded, the project will accelerate construction. overall publicity and set a goal to open traffic on September 2, "said Quynh.

After being opened to traffic, the National Highway 45 - Nghi Son will be 17 meters wide, equivalent to 4 lanes, 2 lanes in each direction, maximum vehicle speed 80km/h (first investment phased phase); In the second investment phase, the Highway 45 - Nghi Son will have a road surface of 34.5 - equivalent to 6 lanes (3 lanes each way), the maximum speed of cars is 120km. /H.

Along with the highway   Nghi Son - Dien Chau (open to traffic September 2, 2023); Mai Son - National Highway 45 (open to traffic April 30, 2023), the opening of Highway 45 - Nghi Son will help the journey from Hanoi to the center of Thanh Hoa province and the center of Thanh Hoa province, the car will move to the center of Thanh Hoa province. transfer by highway.

Highway 45 - Nghi Son expressway project has a length of 43.2 km, started by the Ministry of Transport on July 1, 2021, and is scheduled to be completed in August 2023. The route has a total investment of 8,380 billion VND – budget money. The project is invested with the goal of completing the East North-South Expressway in the 2016-2020 period, along with that, after completing the project route, it will facilitate travel, help people and businesses reduce transportation costs. transport costs